GENESEO – The Village of Geneseo has released a detailed calendar to the community so that public can up to date on the big digs progress.
Sewer main installation is to happen between June 15 and 19. The manhole installation is nearly complete as of Thursday, where crews carefully dug around the underground railroad tunnel extending from 5 Main under Main Street to the Genesee River at Rte. 63 and Court Street.
Beautiful New Listing in Livonia!
585-503-8750
The biggest part of the project, the water main installation in the northbound lane of North Street from the bear fountain to North Street, is set to run fron June 22 to July 22.
Following that, there will be a water main pressure test that will run from July 23 to July 27, then a remedial excavation with sidewalk and concrete work scheduled for July 27 through July 31.
Milling and Paving will follow from August 3 to August 6. The final ‘aesthetic rehabilitation’ will be August 10 to August 14. The final cleanup is scheduled to end on August 20.
See the complete schedule below: